Integrating EV Charging Infrastructure using RE Power and achieving self- sufficiency with Solar + BESS
August 22, 2023
Integrating EV Charging Infrastructure using RE Power and achieving self- sufficiency with Solar + BESS
Segment:
Automobile Group, India
Challenges:
Standalone solar (Off grid Solar) power integrated with BESS based charging stations ensuring that EVs driven are completely carbon neutral. The charging stations would charge 10 Hyundai Kona EV four wheelers.
Solution Supplied
Product Name:
Standalone Solarized EV charging station
System Size:
242 kW Solar + 762 kWh BESS (AC) + EV Charger 50 kW
Newen Scope:
System design and engineering with supply of DC-DC converter 250 kW , Bi-directional inverter 250 KW, Micro Grid Controller
Application:
Newen’s technology will enable batteries to charge during peak shaving from Solar and draw from BESS when energy demand is more than solar output
Customer will be able to reduce fixed charges from the utility at an aggregate plant level
System Supply hours: 9 hours
Customer Benefit
100% Clean energy for Green EV Charging facility
Efficient DC coupled design
Reliable Standalone Solarised EV Charging Station
Future ready: System can be connected to grid for energy export